Project Updates

Look Ahead for Week of May 20th to May 24, 2024

Walker, Construction Grey-Bruce plans to complete the following outlined tasks along Highway 10 from Margaret Street to Campbell Street.

May 21st to May 24th 2024

- Excavate for Retaining Wall

- Strip and Grade for Sidewalk

May 23th to May 24th 2024

- Install new street signs

Note to the public

Sections of the sidewalks will be temporarily closed due to construction activities and for the safety of everyone. Access to businesses will be opened and maintained to the general public.

We please ask everyone not to block the intersection to avoid delays and congestion when the lights turn red. For everyone’s safety, we request that all foot traffic cross the street at the traffic lights where attendants are ready to assist you.


Look Ahead for Week of May 13th to May 17, 2024

Walker, Construction Grey-Bruce plans to complete the following outlined tasks along Highway 10 from Margaret Street to Campbell Street.

May 13th to May 15th 2024

- Parge and Waterproof Storm Structures At or Near the Intersection of County Road 4 and Highway 10.

- Water Sod.

- Remove Temp Asphalt At or Near the Intersection of County Road 4 and Highway 10.

- Remove The Old Pole Base At or Near the Intersection of County Road 4 and Highway 10.

May 16th to May 17th 2024

- Layout Sidewalk and Retaining Wall.

Note to the public

  • Sections of the sidewalks will be temporarily closed due to construction activities and for the safety of everyone. Access to businesses will be opened and maintained to the general public.


Look Ahead for Week of May 6th to May 10th, 2024

Walker, Construction Grey-Bruce plans to complete the following outlined tasks along Highway 10 from Margaret Street to Campbell Street.

May 6th to May 10th 2024 - Parge Storm Structures - Watering Sod -

May 8th to May 10th 2024 - Parge and Moduloc Adjustment - Waterproofing Structures Note to the public

Sections of the sidewalks will be temporarily closed due to construction activities and for the safety of everyone. Access to businesses will be opened and maintained to the general public. 

We please ask everyone not to block the intersection to avoid delays and congestion when the lights turn red. For everyone’s safety, we request that all foot traffic cross the street at the traffic lights where attendants are ready to assist you. Traffic Flow

Traffic controllers will be present to help regulate the flow of traffic during construction. All flow of traffic will be maintained in all directions. No parking is permitted within the construction limits for this duration.


Look Ahead for Week of April 29th to May 3rd, 2024

Walker Construction Grey-Bruce plans to complete the following outlined tasks along Highway 10 from Margaret Street to Campbell Street.

April 29th to May 3rd 2024

- Placement of Topsoil

- Parge Storm Structures

May 1st to May 3rd 2024

- Sodding

Note to the public:

  • Sections of the sidewalks will be temporarily closed due to construction activities and for the safety of everyone. Access to businesses will be opened and maintained to the general public.
  • We please ask everyone not to block the intersection to avoid delays and congestion when the lights turn red. For everyone’s safety, we request that all foot traffic cross the street at the traffic lights where attendants are ready to assist you.

Traffic Flow:

  • Traffic controllers will be present to help regulate the flow of traffic during construction. All flow of traffic will be maintained in all directions. No parking is permitted within the construction limits for this duration.The aforementioned tasks are subject to change in the event of inclement weather and/or unforeseen circumstances encountered.


Update - Tuesday, April 9, 2024

The Flesherton Connecting Link Reconstruction project will be starting up again the week of April 29 (weather dependent)

A summary of the work to be finished includes;

  • Topsoil & sodding boulevards
  • Finish remaining concrete curb & sidewalks
  • Prepare road surface for final lift of asphalt
  • Place asphalt
  • Line Painting & Signs

It is expected that all work will be completed by May 23rd but we should probably allow a couple week buffer.


Update - Friday, December 15, 2023

The Connecting Link project is wrapping up for the year. Walker's will be onside Monday, Dec 18th and Tuesday, Dec 19th doing cleanup however, no further lane closures are required.

Thank you for your patience and cooperation during this project.


Remaining Work for 2024:

- Work which was not completed in 2023

-Placement of Final Asphalt Layer

- Restoration Works



Project Background

It was announced in early April that Grey Highlands had been selected for funding through the Ministry of Transportation's 2023-24 Connecting Link Program to receive up to $3,000,000 of the overall project costs for reconstructing Toronto Road and Sydenham Street in Flesherton. This project had been approved as part of the 2023 budget, pending funding approval.


R.J. Burnside and Associates prepared the tender package and it was issued on Biddingo in accordance with the Procurement By-law on April 26, 2023. Five bid submissions were received. The three lowest bids were reviewed for completeness and mathematical accuracy and were compliant, except for a minor mathematical error with one of the bidders.


Staff supports the recommendation of RJ Burnside that the Municipality award the contract for the Highway 10 Connecting Link at Flesherton to Harold Sutherland Construction at their tendered price of $3,187,946 (HST excluded). A requirement of the tender was for the contractor to provide a Public Relations Officer.

Upon award of the contract and start-up meeting, schedules for public consultation and communications to residents and businesses will be laid out.

A Public Information Session was held Wednesday, July 12th at the Kinplex in Flesherton where staff and contractors were on hand to answer questions and project boards were displayed throughout the room with the project details.


The 2023 approved budget for the Flesherton Connecting Link project is $3,491,873. The MTO funding will provide 90% up to a maximum of $3,000,000 of funding towards the project. The Municipality's portion is to be funded through debenture. The lowest bid provided by Harold Sutherland Construction is $3,187,946 (excluding HST).


The total cost including the non-rebatable portion of HST is $3,244,053.85. There are a number of provisional items included in the tender which will impact the final cost of the work.


The Municipality's budget for the construction work including contingencies is $3,137,412.75. In addition, the estimate of $282,367.15 from RJ Burnside has been allocated in the budget for detailed design engineering and contract administration on the project.